Checkpoints and the PAAR
Checkpoint A before the Form M, Checkpoint B after the PAAR, and the lanes.
Guides
Checkpoint A, before the Form MCheckpoint A checks an import before the Form M: it classifies every line, checks the documents, value and permits, works out the duties and predicts the lane, so you can fix things early.3 min read · 6 answersCheckpoint B, after the PAARCheckpoint B checks the declaration against the PAAR customs issued, line by line, before you lodge. It passes as Ready to lodge, or stops as blocked with the line and figures that differ.3 min readAdding the PAAR to a declarationOnce Checkpoint A has passed, add the PAAR customs issued: upload it for Nohena to read, or enter its assessed value, lane and query status by hand. Then run Checkpoint B.2 min read · 5 answersWhat the four lanes meanCustoms routes every import to one of four lanes: green, blue, yellow or red. Nohena predicts how likely each lane is and what drives it, so you can act before you lodge.2 min read · 1 answer
Videos
Quick answers
Checkpoint A, before the Form M
- Does running Checkpoint A again charge me again?A re-run is quoted on its button before anything is held; if the declaration has not changed since the last run, the existing result is returned and the hold is released in full.
- What does 'Checkpoint A could not finish' mean?Every line was classified, but Checkpoint A did not complete on Nohena's side; nothing was charged for it, so open the declaration and press Run Checkpoint A to try again.
- What does 'Classification is still running' mean?No new line was answered for about three minutes while you waited; Checkpoint A continues on the same credit, so press Continue Checkpoint A again in a moment.
- What happens after I accept the Checkpoint A quote?Nohena classifies every line, showing how many are done and the time left, then runs Checkpoint A; you can continue in the background, and the bell tells you when the result is ready.
- What is on the Checkpoints A and B tab?It holds the Checkpoint A and Checkpoint B cards with their results and buttons, the four-lane prediction, and after hand-off the How did it clear? card.
- Why can I not press Run Checkpoint A?The button is greyed out while Checkpoint A is already classifying or running, and for viewers and billing admins, whose role can read consignments but not run checks.
Adding the PAAR to a declaration
- How do I replace a PAAR that customs amended or re-issued?On the Checkpoints A and B tab, select Replace the PAAR and say why; the PAAR on file stays in the record, and you add the new one and run Checkpoint B again.
- I uploaded the PAAR but the status did not change. Why?If the status still reads Ready for Form M after an upload, the PAAR could not be read well enough to apply; upload a clearer copy, or enter its values by hand.
- What is a PAAR?The PAAR (pre-arrival assessment report) is customs' assessment of an import, issued from the registered Form M and the final shipping documents; it sets the classification and value customs accepts.
- Why does Checkpoint B say no PAAR is on file?Checkpoint B compares the declaration with the issued PAAR, so it is refused until a PAAR is uploaded or its values are entered by hand.
- Why is my manual PAAR entry refused?Each field has a rule: the assessed value must be a naira total above zero, any lane must be green, blue, yellow or red, and you must answer yes or no to whether the PAAR was queried.